1

Closed

Multiple Schedules are not being run

description

Currently only the first schedule which is attached to the job is being used. The system needs to be modified to use more than one schedule.
Closed Feb 7, 2009 at 9:08 PM by mrdenny
Multiple schedules appear to be working.

comments

mrdenny wrote Feb 1, 2009 at 5:27 AM

Code to correct this has been added and is being tested.

mrdenny wrote Feb 1, 2009 at 8:53 PM

Code has been completed and tested. Next release will include changes.

** Closed by mrdenny 2/1/2009 12:14 AM

mrdenny wrote Feb 1, 2009 at 8:53 PM

Need to rework the job schedule piece. The secondary schedules aren't working correctly. The job history data that is being used to figure out the last run time is job specific, not schedule specific.